• CONTRACT AMOUNT: 213,843
  • INDUSTRY:Mining/Metals
  • CLIENT:Ash Grove Cement Company
  • LOCATION:Memphis, TN
  • COMPLETION YEAR: 2017

Northwest Demolition was contracted by a repeat client for a selective removal project at one of their cement terminal facilities in Tennessee.  Scope included the demolition of a compressor building, rail unloader facility, and cement storage complex.  The project included the removal of bulk materials, asbestos, and universal waste.  Additional coordination was required to ensure that the remainder of the facility, which continued operations as normal, was not disturbed by the demolition activities. The project was completed on schedule and without incident.